检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:王德库[1,2] 谭春 隋伟[1,2] Wang Deku;Tan Chun;Sui Wei(China Water Northeastern Investigation,Design&Research Co.,Ltd.,Changchun 130000,China;Research Center on Cold Region Engineering Ministry of Water Resources,Changchun 130000,China)
机构地区:[1]中水东北勘测设计研究有限责任公司,吉林长春130000 [2]水利部寒区工程技术研究中心,吉林长春130000
出 处:《山西建筑》2021年第24期163-165,共3页Shanxi Architecture
摘 要:大藤峡水利枢纽工程坝基软硬岩互层及交错变化复杂,且泄水闸闸门推力较大,为保证工程安全性,对其稳定性水平进行分析与研究。以三维裂隙网络为基础,获取了坝基岩体内部裂隙的连通率和岩体等效力学参数,然后采取数值模拟(离散单元法)的方法对泄水闸28号坝段基础的稳定性模拟与分析。分析结果表明闸坝与坝基整体稳定较好,符合安全需求。The dam foundation of the Datengxia water conservancy project is interbedded with soft and hard rocks with complex staggered changes,and the sluice thrust of the sluice gate is relatively large.In order to ensure the safety of the project,its stability is studied.Based on the three-dimensional fracture network,the connectivity and equivalent mechanical parameters of fractures in dam bedrock were obtained,and then the stability of dam foundation of sluice 28#was simulated and analyzed by numerical simulation(discrete element method).The analysis results showed that the overall stability of sluice and dam foundation is good and meets the safety requirements.
分 类 号:TV698.2[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.30