作 者:鞠兴军 张周爱 智晓峰 田羽 李新鹏 李建刚[2] 王永军 JU Xing-jun;ZHANG Zhou-ai;ZHI Xiao-feng;TIAN Yu;LI Xin-peng;LI Jian-gang;WANG Yong-jun(Shenhua Baorixile Energy Industry Co.,Ltd.,Hulun Buir 021000,China;Research Institute of Technology and Equipment for the Exploitation and Utilization of Mineral Resources,Liaoning Technical University,Fuxin 123000,China;Opencast Mining Institute,Inner Mongolia Coal Mine Design Institute,Hohhot 010010,China)
机构地区:[1]神华宝日希勒能源有限公司,内蒙古呼伦贝尔021000 [2]辽宁工程技术大学矿产资源开发利用技术及装备研究院,辽宁阜新123000 [3]内蒙古煤矿设计研究院露天采矿所,内蒙古呼和浩特010010
出 处:《煤炭工程》2021年第11期21-25,共5页Coal Engineering
基 金:辽宁省教育厅科学技术研究(面上项目)资助项目(LJKZ0342)。
摘 要:针对破碎机选型设计的方法和计算公式以经验为主、理论依据缺乏,半连续工艺系统生产能力计算方法与实际不符等问题,分析重型板式给料机选型参数和生产能力计算方法、物料最大尺寸与破碎机滚筒直径的关系式、物料含水率、作业温度与设备技术生产能力的关系、半连续工艺系统利用率和有效作业时间的确定方法等关键技术,完善了双齿辊破碎机主要技术参数的选型设计方法。基于同步系数,修正了系统利用率计算公式,提出符合实际工况的半连续开采工艺系统生产能力计算的方法。以内蒙古某露天矿半连续工艺系统为实例,验证方法的正确性,为解决半连续工艺设计和实际应用中面临的问题提出思路和方法。In view of the problems that the selection method and calculation formula of crusher are mainly based on experience, lack of theoretical basis, and the calculation method of production capacity of semi continuous process system is inconsistent with the reality, we analyzed the selection parameters and production capacity calculation method of heavy plate feeder, the relationship between the maximum size of material and the diameter of crusher drum, the moisture content of material, the relationship between operating temperature and equipment technical production capacity, the utilization rate of semi continuous process system and the determination method of effective operating time and other key technologies, and improved the selection and design method of main technical parameters of double toothed roll crusher. Based on the synchronization coefficient, the calculation formula of system utilization is modified, and a method was proposed for calculating the production capacity of semi continuous mining process system in line with the actual working conditions. Taking a semi continuous process system of an open pit mine in Inner Mongolia as an example, the correctness of the method was verified, and ideas and methods were put forward to solve the problems faced in semi continuous process design and practical application.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.129.17.22