检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:李军华 刘朝建 LI Junhua;LIU Zhaojian(Sinohydro Bureau 9 Xizang Construction Engineering Co., Ltd., Lhasa 850000, China)
机构地区:[1]水电九局西藏建设工程有限公司,西藏拉萨850000
出 处:《水电与新能源》2021年第11期49-55,共7页Hydropower and New Energy
摘 要:碾压混凝土坝施工的主要特点为高效、快速、连续上升,在高海拔峡谷地区河谷较深、地形狭窄,坝体上部结构复杂,常态混凝土与碾压混凝土在施工过程中往往穿插进行,大型施工设备及施工临建设施布置等均存在较大困难。通过对DG水电站大坝的临建设施优化、施工道路布置优化、施工机械设备配置优化以及大坝材料分区优化,保证了大坝施工质量,虽成本有所增加,但减小了干扰,加快了大坝施工进度。The main advantages of the roller compacted concrete dam construction are high efficiency,fast speed and continuous placing.While for the projects in the high altitude and canyon areas,various issues such as the deep valley,narrow site,complex structure of the upper dam body,and the alternate construction processes of the normal concrete and the roller compacted concrete lead to great difficulties in the arrangement of large construction equipment and temporary facilities.In DG Hydropower Station project,optimization work is carried out on the temporary facility arrangement,construction road layout,construction mechanical equipment selection,and material zoning of the dam body.Although the cost is increased,the construction quality of the dam is guaranteed and the construction progress is accelerated with less interference.
关 键 词:碾压混凝土坝 峡谷地区 临建设施 施工道路 机械设备 合理布置 高效施工
分 类 号:TV642.2[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.82