新时代背景下高端物流仓库(双层)混凝土结构超长无缝设计与施工  被引量:4

Super Long Seamless Design and Construction of High-end Logistics Warehouse(Double-layer)Concrete Structure under Background of New Era

在线阅读下载全文

作  者:连玉 陈绍游 Lian Yu;Chen Shao-you

机构地区:[1]普洛斯投资(上海)有限公司,上海200135 [2]深圳安普发展有限公司,上海200135

出  处:《建筑技术开发》2021年第24期52-53,共2页Building Technology Development

摘  要:以笔者负责的双层高端物流仓库项目为例,从设计到施工介绍了新时代背景下高端物流仓库超长混凝土结构无缝设计与施工,即采用膨胀加强带和预应力相结合的施工工艺代替传统的结构变形缝、后浇带施工工艺,彻底解决了物流仓库施工周期长、刚性接缝多、漏水隐患及施工难的问题。主要介绍这种高端仓库的无缝设计与施工工艺。Taking one of several double-layer high-end logistics warehouse projects in the author’s charge as an example,from design to construction,this paper introduces the seamless design and construction of super long concrete structure of high-end logistics warehouse under the background of the new era,that is,the construction technology of the combination of expansion reinforcing belt and prestress is used to replace the traditional construction technology of structural deformation joint/post pouring belt,The problems of long construction period,many rigid joints,hidden dangers of water leakage and difficult construction of logistics warehouse are completely solved.This paper mainly introduces the seamless design and construction technology of this high-end warehouse.

关 键 词:超长混凝土无缝设计 经济性 膨胀加强带 预应力 

分 类 号:TU755[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象