摘  要:介绍了蒙山县壬山水库工程的施工导流方案优化设计变更内容。从施工工期、施工条件、对环境的影响和施工成本等方面,结合实际工程进度与环境条件,对枯水期分期导流方案和隧洞全年导流方案进行比选,推荐采用枯水期分期导流方案作为施工导流的优化设计变更方案。该方案能确保整体施工安全及满足进度要求,并具有节省投资和保护环境的优势。An introduction was made on the contents of optimization design change of construction diversion scheme for Renshan Reservoir Project in Mengshan County.Combined with the actual construction progress and environ⁃mental conditions,the scheme of staged diversion in dry season was compared with the year-round tunnel diversion scheme in respects of construction schedule,construction conditions,environmental impact and construction cost etc,based on which the staged diversion scheme is recommended as the optimized design change scheme since it is able to ensure the overall construction safety and meet the schedule requirements,and has the advantages of saving investment and environmental protection.

关 键 词:壬山水库 施工导流方案 枯水期分期导流 设计变更 

分 类 号:TV551.16[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象