CAP1400常规岛主厂房基础底板施工管理  

MAIN PLANT BUILDING FOUNDATION BOTTOM CONSTRUCTION MANAGEMENT ON CAP1400 CONVENTIONAL ISLAND

在线阅读下载全文

作  者:杨勇 YANG Yong(Shanghai Electric Power Transmission and Distribution Engineering Complete Set Co.,Ltd.,200050,Shanghai,China)

机构地区:[1]上海电气输配电工程成套有限公司,上海200050

出  处:《建筑技术》2022年第2期152-154,共3页Architecture Technology

摘  要:CAP 1400常规岛主厂房采用半地下箱形基础。因底板结构混凝土浇筑体量大,施工周期长,施工组织中需对结构底板进行合理分区,实现多线路流水施工;采用免拆模板技术,减少凿毛工作量。采用模块化养护棚实现了大体积混凝土冬期浇筑及养护全天候施工。The main plant building on CAP1400 conventional island adopts semi-basement box foundation. Considering large concrete grouting volume of bottom structure and long construction period,the structural bottom construction shall be effectively divided during construction, to realize multiple flow construction;permanent formwork technique was adopted to reduce coarsening workload. Modular curing shed was used to realize all weather construction of massive concrete grouting and curing in winter.

关 键 词:常规岛底板 合理分区 免拆模板 全天候施工 

分 类 号:TU753[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象