金沙水电站二、三期导截流施工方案分析  被引量:2

Analysis on construction scheme of second and third phase river diversion and closure works of Jinsha Hydropower Station

在线阅读下载全文

作  者:刘同林 LIU Tonglin(Sichuan Ertan International Engineering Consulting Co.,Ltd.,Chengdu 611130,China)

机构地区:[1]四川二滩国际工程咨询有限责任公司,四川成都611130

出  处:《水利水电快报》2022年第3期10-13,共4页Express Water Resources & Hydropower Information

摘  要:金沙水电站导截流工程具有流速大、截流落差高、施工工期紧等特点。为保证截流成功,利用水力学计算并开展模型试验,选取了预进占单戗立堵截流、截流戗堤与围堰分开布置的方法进行施工。结果表明:针对河道较宽和导流明渠狭窄、流速大的情况,预进占单戗立堵截流能有效降低截流风险和截流难度,可实现快速截流并降低投资成本。研究成果可为类似工程提供参考。Aiming at the characteristics of diversion and closure project in Jinsha Hydropower Station,such as high flow velocity,high closure drop,and tight construction period,to ensure a successful closure,we used hydraulic calculations and model test results to select the construction method of pre-advance occupancy and vertical block⁃ing and the separation of closure levee and cofferdam.The results showed that in the case of wide river,narrow di⁃version channel and high flow rate,pre-advance occupancy and vertical blocking could effectively reduce the risk and difficulty of river closure,achieve rapid closure and reduce the investment cost.The research result could pro⁃vide reference for similar projects.

关 键 词:导截流 围堰工程 导流明渠 金沙水电站 

分 类 号:TV551.1[水利工程—水利水电工程]

 