秦山核电厂低压厂变和380V工作段扩容设计及施工方案探讨  

Discussion on Capacity Expansion Design and Construction Scheme of Low Voltage Station Transformer and 380 V Working Section in Qinshan Nuclear Power Plant

在线阅读下载全文

作  者:孙玉朋 马永立 蒋军 薛坤 SUN Yupeng;MA Yongli;JIANG Jun;XUE Kun(CNNC Nuclear Power Operation Management Co.,Ltd.,Haiyan 314300,China)

机构地区:[1]中核核电运行管理有限公司,浙江海盐314300

出  处:《电工技术》2022年第5期197-199,202,共4页Electric Engineering

摘  要:针对秦山核电厂新增两台真空泵机组引起的低压厂变和380 V工作段配电屏容量增加且超过原设计容量的问题,给出了低压厂变和380 V工作段配电屏的改造设计分析及实施方案。该改造于机组OT-118大修(2018年6月)期间实施,改造后设备运行状况良好,说明改造的设计及实施方案是成功的。The capacity of low-voltage station transformer and 380 V working section distribution panel increased and exceeded the original design capacity caused by the addition of two vacuum pump units in Qinshan nuclear power plant.The transformation design analysis and implementation scheme of low-voltage station transformer and 380 V working section distribution panel are given.The transformation was implemented on the site of OT-118 overhaul of the unit(June 2018).After the transformation,the equipment is in good operation,indicating that the design and implementation scheme of the transformation are successful.

关 键 词:变压器 扩容 设计 施工 方案 

分 类 号:TM41[电气工程—电器]

 