作 者:徐凤奎 XU Feng-kui(Power China Guiyang Engineering Corporation Limited,Guiyang 550081,China)
机构地区:[1]中国电建集团贵阳勘测设计研究院有限公司,贵州贵阳550081
出 处:《云南水力发电》2022年第4期274-277,共4页Yunnan Water Power
摘 要:水电工程具有规模大、工期长、地质条件复杂、交通条件普遍较差等特点,涉及大量征地、移民安置、环保等方面的问题,随着水电开发转向藏区,敏感因素增多、自然条件恶劣,在合同履行过程中必然存在不可预见因素和风险,停工窝工现象不可避免,因此高效、合理地处理窝工索赔问题是施工阶段合同管理工作重点和难点。结合水电工程合同管理方面工作经验,就窝工索赔费用计算提出见解,以供交流,共同提高合同管理水平。Hydroelectric projects are characterized by large scale,long construction period,complex geological conditions and generally poor traffic conditions,which involve many problems such as land acquisition,resettlement and environmental protection.With the diversion of hydropower development to Tibetan area,more sensitive factors and harsh natural conditions have arisen.Unforeseeable factors and risks will inevitably exist in the process of contract performance,and suspension is unavoidable.Therefore,it is the key and difficult point of contract management in construction stage to deal with suspension claims efficiently and reasonably.Based on the experience in contract management of hydropower projects,this paper gives some opinions on the calculation of suspension claim cost.
分 类 号:TL372.3[核科学技术—核技术及应用]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:52.14.189.148