白马泾泵站开挖及砼裂缝控制设计  

Excavation of Baimajing Pumping Station and Control Design of Concrete Cracks

在线阅读下载全文

作  者:严谨 李晓丹 刘菲 Yan Jin;Li Xiaodan;Liu Fei(Hubei Water Conservancy and Hydropower Planning,Survey and Design Institute,Wuhan 430070,China)

机构地区:[1]湖北省水利水电规划勘测设计院,湖北武汉430070

出  处:《长江技术经济》2022年第2期98-100,108,共4页Technology and Economy of Changjiang

摘  要:针对白马泾泵站的工程实际情况,结合地形、地质条件及边坡稳定要求,对泵站基础采取分期开挖,局部采用陡边坡开挖,加快了施工进度,减少了开挖工程量及投资。在泵房出水流道砼中掺入聚丙烯纤维并预埋冷却水管,有效控制混凝土裂缝的发生。Aiming at the engineering current situation of BaiMajing pump station,combined with the terrain and geological conditions and the slope stability requirements,we adopted the method of multi-stage excavation to pumping station foundation and the method of steep slope excavation partly,speeding up the construction progress,reducing the excavation quantities and investment.In the pump outlet conduit concrete,mixed with polypropylene fiber and pre-buried cooling water pipe can effectively control the occurrence of the concrete cracks.

关 键 词:泵站工程 基础开挖 裂缝控制 

分 类 号:TV331[水利工程—水工结构工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象