蒲石河抽水蓄能电站1号机转轮改造水力稳定性研究与实践  被引量:2

Research and Practice of Hydraulic Stability Reconstruction of No.1 Unit Runner of Pushihe Pumped-storage Power Station

在线阅读下载全文

作  者:谢文祥 张韬 覃大清[2,3,4] 谢明杰 XIE Wenxiang;ZHANG Tao;QIN Daqing;XIE Mingjie(Liaoning Pushihe Pumped Storage Company Limited,Dandong 118216,China;Hadong National Engineering Research Center Hydro-power Equipment Company Limited,Harbin 150040,China;State Key Laboratory of Hydro-power Equipment(Harbin Institute of Large Electrical Machinery),Harbin 150040,China;Harbin Electric Machinery Company Limited,Harbin 150040,China)

机构地区:[1]辽宁蒲石河抽水蓄能有限公司,辽宁丹东118216 [2]哈动国家水力发电设备工程技术研究中心有限公司,哈尔滨150040 [3]水力发电设备国家重点实验室(哈尔滨大电机研究所),哈尔滨150040 [4]哈尔滨电机厂有限责任公司,哈尔滨150040

出  处:《大电机技术》2022年第3期69-76,共8页Large Electric Machine and Hydraulic Turbine

摘  要:蒲石河抽水蓄能电站自运行以来,机组和厂房振动强烈,给电站带来较大的安全隐患,迫切需要采取措施降低振动。为解决该振动问题,经现场测试数据分析,认为引起水电站厂房100Hz异常振动和噪声的主要激振力是由动静干涉诱发引起的。因此采用了9叶片转轮更换为7叶片转轮的错频降振改造措施。本文通过数值计算、模型试验和真机现场测试等方法,重点比较了7叶片转轮与原9叶片转轮的无叶区压力脉动幅值和现场振动情况。模型试验结果表明,经水力优化,7叶片转轮无叶区压力脉动幅值整体低于原9叶片转轮;同时,改造后原型机现场运行情况表明,机组和厂房异常振动消失,机组振摆、噪音及振动水平均大幅降低,证明了该方案的有效性和可行性,研究成果可应用到具有相同振动问题的抽水蓄能电站的改造中。Since the operation of pushihe pumped-storage power station,the unit and workshop have been vibrated strongly,which has brought great potential safety hazards to the power station.It is urgent to take measures to reduce the vibration.In order to solve the vibration problem,the analysis of the field test data shows that the main excitation force that causes the abnormal vibration and noise of the hydropower plant at 100 Hz is caused by the static and dynamic interference.Therefore,the staggered frequency vibration reduction measures of replacing the 9-blade runner with the 7-blade runner are adopted.This paper focuses on comparing the pressure pulsation amplitude and field vibration of the 7-blade runner and the original 9-blade runner through numerical calculation,model test and real machine field test.The model test results show that,after hydraulic optimization,the pressure pulsation amplitude in the non-blade area of the 7-blade runner is generally lower than that of the original 9-blade runner,and the dynamic and static interference frequency division amplitude is greatly reduced.The abnormal vibration of the unit and the powerhouse disappeared,and the vibration,noise and vibration levels of the unit were greatly reduced,which proved the effectiveness and feasibility of the scheme.The research results can be applied to the reconstruction of the pumped storage power station with the same vibration problem.

关 键 词:蒲石河电站 水泵水轮机 稳定性 模型试验 7叶片转轮 

分 类 号:TK730.323[交通运输工程—轮机工程]

 