首钢长钢9号高炉长期休风快速恢复炉况实践  被引量:1

Practice of Rapid Recovery of No.9 Blast Furnace of Shougang Changgang

在线阅读下载全文

作  者:郝文龙 王凯[1] 张红斌[1] 刘小龙[1] Hao Wenlong;Wang Kai;Zhang Hongbin;Liu Xiaolong(Ironmaking Plant of Shougang Changzhi Steel&Iron Co.,Ltd.,Changzhi Shanxi 046031)

机构地区:[1]首钢长治钢铁有限公司炼铁厂,山西长治046031

出  处:《山西冶金》2022年第5期97-99,共3页Shanxi Metallurgy

摘  要:首钢长钢9号高炉历次休风炉况恢复时间长,炉缸工作状态欠佳。针对此问题,通过制定合理的修复风方案,首次实现了双铁口出铁休风,实际休风时间26.86 h;通过合理测算渣碱度、休风期间采取炉体保温措施,用时16.96 h恢复至全风,比过去同类休风节约10 h。此次实践成效显著,可为今后长期休风实现快速恢复炉况积累经验。The recovery time of No.9 blast furnace of Shougang Changgang is long,the hearth working condition is poor.In order to solve this problem,by formulating a reasonable air restoration scheme,the air off at the double iron outlet was realized for the first time,and the actual time of air off was 26.86 h.By reasonably measuring the slag alkalinity and taking measures such as furnace body heat preservation during wind off,it took 16.96 hours to recover to full air,saving 10 hours compared with similar wind off in the past.Great progress has been made in this practice,and valuable experience has been accumulated for realizing rapid recovery of furnace condition after long-term wind shutdown in the future.

关 键 词:高炉 长期休风 炉况 快速恢复 

分 类 号:TF544.7[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象