10 kV开关柜改造可行性研究  

Feasibility Study on Transformation of 10 kV Switchgear

在线阅读下载全文

作  者:宋立伟 王海兵 SONG Liwei;WANG Haibing(Sujin Shuozhou Gangue Power Generation Co.,Ltd.,Shuozhou 036800)

机构地区:[1]苏晋朔州煤矸石发电有限公司,山西朔州036800

出  处:《电力安全技术》2022年第10期48-52,共5页Electric Safety Technology

摘  要:某电厂投产后,发生多起因10 kV开关柜故障引起的全厂停电和机组停运事件。专业人员进行缺陷和隐患排查以及可靠性分析,查明现有10 kV开关柜存在质量问题。为提高10 kV系统设备的可靠性,从而保证机组安全稳定运行,提出10 kV开关柜备选改造方案。经施工安全分析、投资估算、经济评价,认为方案三可行。A multiple of station blackouts and unit shutdowns occurred due to 10 kV switchgear failures since the initial operation of a power plant.Professionals carry out defect and hidden danger troubleshooting and reliability analysis,and quality problems are find out in the existing 10 kV switchgear..In order to improve the reliability of 10 kV system equipment and ensure the safe and stable operation of the unit,several alternative transformation schemes for 10 kV switchgear is proposed.Based on construction safety analysis,investment estimation and economic evaluation,the third scheme is considered feasible.

关 键 词:全厂停电 机组停运 隐患排查 开关柜 

分 类 号:TM591[电气工程—电器]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象