拉姆2水电站引水竖井施工方案研究  

Research on Construction Scheme of Headrace Shaft for Ramu-2 HPP

在线阅读下载全文

作  者:吴建军 宋自平 WU Jianjun;SONG Ziping(International Engineering Company of Sinohydro Bureau 10th Co.,Ltd.,Chengdu,Sichuan 610037)

机构地区:[1]中国水利水电第十工程局有限公司国际公司,四川成都610037

出  处:《四川水力发电》2022年第5期70-73,81,共5页Sichuan Hydropower

摘  要:拉姆2水电站引水竖井和竖井底部的高压隧洞为该工程引水系统施工的难点,且其高压隧洞处于施工关键线路上,不具备作为引水竖井底部施工通道的条件。阐述了对引水竖井与调压井布置方案进行调整的建议方案,即将两井采用相同的中心线合并布置,采用矿山快速正井法施工方案开挖竖井以减少施工临建成本和措施费用,缩短了施工工期。The headrace shaft and the high-pressure tunnel at the bottom of the shaft in Ramu-2 HPP pose challenges for the construction of the headrace system,and the high-pressure tunnel is on the critical path of the construction process,which cannot be used as the bottom construction access of the headrace shaft.The authors suggest that the layout scheme of the headrace shaft and surge shaft be adjusted.In the adjusted scheme,the two shafts are arranged by sharing the same center line,and the fast downward excavating method is adopted to reduce the cost of temporary facilities construction and measures,as well as shorten the construction period.

关 键 词:拉姆2水电站 引水竖井 调压井 同中心线合并布置 正井法施工 施工方案 研究 

分 类 号:TV7[水利工程—水利水电工程] TV52TV51TV554

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象