大型预制墩台安装分离式柔性止水结构施工  

Construction of Separated Flexible Water Stop Structure for Installation of Large Prefabricated Pier and Abutment

在线阅读下载全文

作  者:林锦楷 陈秋竹 LIN Jin-kai;CHEN Qiu-zhu(China Communications 2nd Navigational Bureau 2nd Engineering Co.Ltd.,Chongqing 401121,China)

机构地区:[1]中交二航局第二工程有限公司,重庆市401121

出  处:《公路》2022年第11期179-184,共6页Highway

摘  要:在厦门第二东通道预制墩台安装施工过程中,湿接缝施工对止水要求较高。若止水效果不好,将会直接影响湿接缝的施工质量和耐久性。为解决湿接缝施工时的止水问题,运用分离式柔性止水结构实现承台预留孔与钢管桩之间的止水,使用无预埋件钢套箱实现预制承台顶面与钢套箱的止水,并成功在23个墩台安装施工中使用,表明该止水施工工艺可行。During the installation and construction of prefabricated piers and abutments of the Xiamen Second East Passage Project, the construction of wet joint imposes high requirements for water stop. The effect of water stop will directly affect the construction quality and durability of the wet joint. In order to solve the problem of water stop during wet joint construction, the separated flexible water stop structure is used to realize the water stop between the reserved hole of the bearing platform and the steel pipe pile, and the steel casing without embedded parts is used to realize the water stop between the top surface of the prefabricated bearing platform and the steel casing. The scheme has been successfully used in the installation and construction of 23 piers and abutments of the Project, which shows that the water stop construction technology is feasible.

关 键 词:桥梁工程 预制墩台 分离式柔性止水 无预埋件钢套箱 

分 类 号:U445.559[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象