防洪调蓄湖引水工程引水规模论证  

Demonstration on Water Diversion Scaleof Diversion Project for Flood Control and Lake Storage

在线阅读下载全文

作  者:帅志勇 SHUAI Zhiyong(Water Resources Protection Center,Ganfu Plain,Nanchang County,Nanchang 330200,China)

机构地区:[1]南昌县赣抚平原水资源保护中心,江西南昌330200

出  处:《河南水利与南水北调》2022年第11期15-16,共2页Henan Water Resources & South-to-North Water Diversion

摘  要:以某防洪调蓄湖项目为研究对象,针对项目设计部门所提出的设计目标,进行了引水工程引水规模的论证探讨。分析表明,该防洪调蓄湖换水周期应按30 d确定,引水泵站每天运行时间约2 h,以增强湖区的水体流动性。待远期一工段引水工程周边调蓄湖均建成后能有效改善整个片区的水质,并形成“调蓄低地+外排外江”的排涝总体格局,大大提高防洪治涝总体能力,构建起完善可靠的城市防洪治涝体系。Taking a project of flood control and lake storage as the research object, this paper discusses the scale of water diversion project according to the design goal put forward by the project design department. The analysis shows that the water exchange cycle of the flood control and storage lake should be determined as 30 days, and the operation time of the diversion pump station should be about 2 hours per day in order to enhance the water flow in the lake area. The water quality of the whole area can be effectively improved after the completion of the regulation and storage lakes around the water diversion project of the first section in the long term, and the overall pattern of“regulation and storage of lowlands+drainage of rivers”will be formed, which will greatly improve the overall capacity of flood control and waterlogging control, and build a sound and reliable urban flood control and waterlogging control system.

关 键 词:防洪调蓄湖 引水工程 引水规模 

分 类 号:TV131[水利工程—水力学及河流动力学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象