西山水库工程来沙量的计算分析  

Calculation and Analysis of Sediment Discharge from Western Hills Reservoir Project

在线阅读下载全文

作  者:张芳齐 ZHANG Fang-qi

机构地区:[1]太原理工大学建筑设计研究院有限公司,山西太原030024

出  处:《山西水利科技》2022年第4期36-39,共4页Shanxi Hydrotechnics

摘  要:对西山水库工程来沙量计算分析,一是为水库除险加固提供依据,二是为无资料地区工程来沙量的计算提供参考。来沙总量包括悬移质和推移质。悬移质来沙量计算采用悬移质输沙模数图法和雨沙模型法两种方法,同时考虑人类活动对悬移质来沙量的影响;推移质计算采用系数法。根据水库运行以来的实际来沙情况,对计算结果进行合理性分析,最终采用雨沙模型法计算结果。The calculation and analysis of the sediment load of the Western Hills Reservoir Project provide a basis for the reinforcement of the reservoir and a reference for the calculation of the sediment load of the project in the area without data. The total sediment inflow includes suspended load and bed load. Suspended load sediment inflow was calculated by suspended load sediment transport modulus diagram method and rainfall sediment model method,taking into account the impact of human activities. The bed load was calculated by coefficient method. According to the actual sediment inflow situation since the operation of the reservoir,the rationality of the calculation results was analyzed,and the calculation results of the rain sediment model method were finally adopted.

关 键 词:西山水库 悬移质 推移质 来沙总量 

分 类 号:TV145[水利工程—水力学及河流动力学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象