明挖深埋隧道下穿施工对高速铁路桥梁的影响  被引量:6

Influence of Underpass Construction of Deep⁃covered Tunnel with Open⁃cut Method on High Speed Railway Bridge

在线阅读下载全文

作  者:孙武鹏 SUN Wupeng(China Railway Shanghai Group Co.Ltd.,Shanghai 200071,China)

机构地区:[1]中国铁路上海局集团有限公司,上海200071

出  处:《铁道建筑》2023年第3期113-117,共5页Railway Engineering

摘  要:甬金高速公路(宁波—金华)改扩建明挖工程下穿杭温高速铁路(杭州—温州)桥梁处挖深超过20 m。本文首先介绍了改扩建明挖工程施工基本原则,然后研究了明挖深埋隧道施工方案,基坑围护、铁路桥墩保护等技术问题,提出对基坑采用钻孔咬合桩+四道内支撑体系围护,对既有高速铁路桥墩基础采用钻孔桩隔离+搅拌桩作为止水帷幕。经数值模拟计算,基坑、高速铁路桥梁桥墩变形均小于规范限值。Ningbo-Jinhua highway reconstruction and expansion project underpassed Hangzhou-Wenzhou high speed railway bridge,and the excavation depth between them exceed 20 m.This paper introduced the basic principles for the reconstruction and expansion project with open-cut method,then studied construction scheme of deep-covered tunnel with open-cut method,and technical issues,such as foundation pit enclosure,railway pier protection.It is proposed to use occlusal piles and four internal support systems for foundation pit enclosure,and for existing high speed railway bridge pier foundations to use bored pile isolation and waterproof curtains with mixing pile.Through numerical simulation,the deformation of foundation pits and high speed railway bridge piers are all less than the specification limits.

关 键 词:高速铁路桥梁 深埋公路隧道 变形控制效果 数值模拟 钻孔咬合桩 止水帷幕 

分 类 号:U448.13[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象