深埋综放工作面过褶曲构造带方案优化选择  被引量:1

Scheme Optimization of Crossing Folding Tectonic Zone at Deeply-buried Fully-mechanized Caving Face

在线阅读下载全文

作  者:王伟 Wang Wei(Intelligent Mine Business Division of No.2 Colliery,Yangquan Coal Industry(Group)Co.,Ltd.,Yangquan,Shanxi 045000)

机构地区:[1]华阳股份智能矿山事业部二矿,山西阳泉045000

出  处:《江西煤炭科技》2023年第2期30-32,39,共4页Jiangxi Coal Science & Technology

摘  要:本文重点探讨华阳集团二矿81104工作面回采期间过构造带技术方案;通过钻孔探测,确定该工作面构造影响范围为1000~1590 m,主要为褶曲构造;基于矿井实际条件,拟定三种过构造带方案;技术经济分析表明,方案一工作面推进用时83天,利润607万元,方案二工作面推进用时100天,利润-1014.08万元,方案三工作面推进用时76天,利润1572万元;显然,方案三为最佳方案。The paper focuses on the technology of crossing tectonic zone during stoping at 81104 working face in No.2 Colliery of Yangquan Coal Industry(Group)Co.,Ltd.,in which three schemes are presented through drilling exploration which determines the tectonic zone is folding with influence area of 1000 to 1590 m.Technical economy analysis show that Scheme 1 can make a profit of 6.07 million Yuan with working face advance time of 83 days;Scheme 2 can make a profit of minus 10.1408 million Yuan with working face advance time of 100 days and Scheme 3 can make a profit of minus 15.72 million Yuan with working face advance time of 76 days which is the optimal obviously.

关 键 词:综放工作面 过褶曲构造 方案优化 

分 类 号:TD823.8[矿业工程—煤矿开采] TD823.97[矿业工程—矿山开采]

 