长距离机械顶管先顶后井施工技术研究与应用  

The research and application of first jacking then well construction technology in long distance mechanical pipe

在线阅读下载全文

作  者:雷琳 Lei Lin(Xi’an Municipal Road&Bridge Construction Group Co.,Ltd.,Xi’an 710016,China)

机构地区:[1]西安市政道桥建设集团有限公司,陕西西安710016

出  处:《山西建筑》2023年第10期111-113,149,共4页Shanxi Architecture

摘  要:长距离机械顶管施工过程中,该技术将组合式中继间应用于越井顶进中,在遵循先顶后井的总体方案下,对中间检查井采用“中继间顶入、周期分层开挖”的施工方法,同时对中间检查井实行“分层、分周期开挖方式”,在保证先顶后井成功的同时,免除了管道破除切割,加快了工程进度,提高了施工的环保性。This technology applies the combined relay chamber to jack over well in the process of long-distance mechanical pipe jacking construction.Following the overall scheme of jacking first and then well,the construction method of“the relay chamber jacking and periodic stratified excavation”is adopted for the intermediate check well.Meanwhile,“stratified and periodic excavation”is implemented for the intermediate inspection.The technology ensures the success of jacking first and then well,exempts the pipeline from breaking and cutting,speeds up the project progress,and improves the construction of environmental protection.

关 键 词:机械顶管 中间检查井 先顶后井 中继间 

分 类 号:TU943.9[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象