西柏树矿巷道预注浆技术研究及应用  被引量:5

Research and application of roadway pre-grouting technology in Xibaishu Mine

在线阅读下载全文

作  者:张琳 孟庆学 宋德林 张晓龙 Zhang Lin;Meng Qingxue;Song Delin;Zhang Xiaolong(Inner Mongolia Baotou Xinda Gold Mining Co.,Ltd.;Institute of Mining and Coal,Inner Mongolia University of Science&Technology)

机构地区:[1]内蒙古包头鑫达黄金矿业有限责任公司 [2]内蒙古科技大学矿业与煤炭学院

出  处:《黄金》2023年第5期24-27,共4页Gold

摘  要:西柏树矿24号脉855 m中段西脉外运输巷围岩破碎,伴随有较大涌水,使得掘进存在安全隐患大、单班台效低、支护费用高等问题。为了确保巷道掘进的安全及效率,提出了超前探水结合超前预注浆、超前长锚杆支护技术措施,给出了注浆孔工程布置、注浆工艺参数,并进行了现场应用。结果表明:使用超前预注浆堵水、注浆加固,结合超前锚杆,保证了掘进速度,安全系数大大增加,有效减少了人员在淋水环境下作业时间,取得了月进尺45 m,支护成本下降13%的经济技术指标,可为类似矿山提供参考。The surrounding rock of the haulage way outside the 855 m level of the No.24 vein in Xibaishu Mine of Xinda company is broken,accompanied by a large amount of water gushing,which makes the excavation problematic with great potential safety hazards,low single-shift platform efficiency,and high support costs.To ensure the safety and efficiency of roadway excavation,the technical measures of in-advance water exploration combined with in-advance pre-grouting and in-advance long bolt support are put forward,the engineering layout of grouting holes and grouting process parameters are given,and the experimental research is carried out.The test results show that the use of in-advance pre-grouting for water plugging,grouting reinforcement,and in-advance bolt can ensure the excavation progress,greatly increase the safety coefficient,effectively reduce the operation time of personnel in the water-pouring environment,and obtain the economic and technical index of 45 m monthly footage and 13%reduction of support costs,which can provide references for similar mines.

关 键 词:巷道掘进 破碎围岩 涌水 预注浆加固 超前锚杆支护 

分 类 号:TD265.4[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象