运营隧道保护区进行大型盾构部件吊装的分析与研究  

Analysis and Researchon Hoisting of Large Shield Components in Protection Area of Tunnel in Operation

在线阅读下载全文

作  者:黄嘉杰 HUANG Jiajie(Shanghai Foundation Engineering Group Co.,Ltd.,Shanghai 200002,China)

机构地区:[1]上海市基础工程集团有限公司,上海200002

出  处:《建筑施工》2023年第6期1179-1181,共3页Building Construction

摘  要:为减少大型盾构吊装阶段对隧道运营保护区的不利影响,以上海江浦路越江隧道新建工程江中段的大型盾构部件刀盘吊装施工为例,充分考虑吊装阶段的每步工序,依次采用吊装设备选型、受力计算模拟、制定专项方案等方法,将吊装阶段产生的沉降及侧向位移控制在相关规范允许范围内,为国内隧道运营保护区大型盾构部件吊装提供一种可供参考的施工流程。To reduce the adverse impact of the hoisting stage of large shield tunneling on the tunnel operation protection area,taking the hoisting construction of the large shield tunneling component cutterhead in the Jiangzhong section of the Shanghai Jiangpu Road Cross River Tunnel as an example,each step of the hoisting stage is fully considered,the methods such as selecting hoisting equipment,simulating force calculation,and developing a special plan are sequentially adopted to control the settlement and lateral displacement generated during the hoisting stage within the allowable range of relevant regulations,which can provide a reference construction process for the hoisting of large shield tunneling components in tunnel operation protection area in China.

关 键 词:盾构 大型盾构吊装 运营隧道保护区 工况分析 

分 类 号:TU99[建筑科学—市政工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象