高家塔三级泵站直流电源系统负荷统计及容量计算  

Load Statistics and Capacity Calculation of Direct Current Power Supply System in Gaojiata Three-Stage Pumping Station

在线阅读下载全文

作  者:高璐 王含羽 解辰[1] GAO Lu;WANG Hanyu;XIE Chen(Shaanxi Province Institure of Water Resources and Elactrice Power Investigation and Design,Xi’an 710001,China)

机构地区:[1]陕西省水利电力勘测设计研究院,陕西西安710001

出  处:《通信电源技术》2023年第13期73-75,共3页Telecom Power Technology

摘  要:根据高家塔三级泵站工程中电气二次设备的详细配置,结合三级泵站的机组运行工况,通过统计分析泵站内直流电源系统各阶段设备负荷(经常负荷、事故负荷、冲击负荷),确定各阶段的负荷容量,进而更加准确地计算直流电源系统的蓄电池容量。直流电源系统设计严格贯彻安全适用、技术先进、经济合理的原则,满足安全可靠、技术先进的要求。According to the detailed configuration of the electrical secondary equipment in Gaojiata three-stage pumping station project,combined with the unit operating conditions of the three-stage pumping station,through the statistical analysis of the equipment load(direct current continuous load,direct current emergency load,direct current momentary load)of the direct current power supply system in the pumping station,the load capacity of each stage is determined,and then the battery capacity of the direct current power supply system is calculated more accurately.

关 键 词:直流电源系统 直流负荷 蓄电池容量 阶梯法 

分 类 号:TM721.1[电气工程—电力系统及自动化]

 