观音岩水电站右岸大坝固结灌浆试验研究  

Experimental Study on Consolidation Grouting for Right Bank Dam of Guanyinyan Hydropower Station

在线阅读下载全文

作  者:李贵平 LI Guiping(China Anneng Group First Engineering Bureau Co.Ltd.,Nanning 530200 China)

机构地区:[1]中国安能集团第一工程局有限公司,广西南宁530200

出  处:《红水河》2023年第4期52-56,共5页Hongshui River

摘  要:为获得观音岩水电站右岸大坝基础固结灌浆设计参数,选择合适的试验区开展了固结灌浆试验。笔者详细介绍了试验目的、灌浆孔布置、试验方法及成果,并对试验成果进行了分析。结果表明,固结灌浆参数选择合理,施工方法可行,处理效果明显。研究成果可为该工程固结灌浆施工提供依据。In order to obtain the design parameters of consolidation grouting for the right bank dam foundation of Guanyinyan Hydropower Station a suitable test area was selected to carry out the consolidation grouting test.The author introduces the test purpose grouting hole arrangement test method and results in detail and analyzes the test results.The results show that the selection of consolidation grouting parameters is reasonable the construction method is feasible and the treatment effect is obvious.The research results can provide a basisfor the consolidation grouting construction of the project.

关 键 词:固结灌浆 设计参数 压水试验 观音岩水电站 

分 类 号:TV543.5[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象