作 者:裴强 PEI Qiang(The Third Engineering Co.,Ltd.of China Railway 12th Bureau Group,Taiyuan 030024,China)
机构地区:[1]中铁十二局集团第三工程有限公司,太原030024
出 处:《价值工程》2023年第26期66-68,共3页Value Engineering
摘 要:以成昆铁路扩能改造工程旺牛村双线隧道下穿京昆高速公路为例,通过实施单循环超长管棚工作间一次性穿越高速公路段落的工艺,大大缩短下穿公路的时间,有利于控制围岩变形量。在隧道开挖时采取了微差控制爆破技术和初期支护过程中全过程利用信息化监控手段及时上传变形数据,有利于及时掌握围岩变形,确保开挖安全。Taking the Wangniucun double track tunnel of the Chengdu Kunming Railway expansion and renovation project as an example,the process of one-time crossing of the expressway section through a single cycle ultra long pipe shed workshop is implemented,which greatly shortens the time of crossing the highway and is conducive to controlling the deformation of surrounding rock.The use of millisecond controlled blasting technology during tunnel excavation and the use of information monitoring methods throughout the initial support process to timely upload deformation data are conducive to timely understanding of surrounding rock deformation and ensuring excavation safety.
关 键 词:单循环管棚工作间 微差控爆技术 下穿高速公路浅埋段
分 类 号:U25[交通运输工程—道路与铁道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.135.220.9