检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:范磊 薛广记 舍跃斌 谌文涛 冯猛 FAN Lei;XUE Guangji;SHE Yuebin;CHEN Wentao;FENG Meng(China Railway Engineering Equipment Group Co.,Ltd.,Zhengzhou 450016,Henan,China)
机构地区:[1]中铁工程装备集团有限公司,河南郑州450016
出 处:《隧道建设(中英文)》2023年第9期1605-1613,共9页Tunnel Construction
基 金:国家重点研发计划(2020YFB1712105)。
摘 要:为解决复合地层矩形顶管机施工难题,探讨矩形顶管机在不同复合地层中的技术方案,以重庆天宫殿下穿快速路隧道项目为依托,对用于软土与岩层复合地层的矩形顶管机开挖、出渣等关键系统设计及应用进行研究。首次提出复合地层分层开挖方式,开发出盲区开挖装置(破岩滚筒),并基于有限元及工业试验分析,验证复合多刀盘+滚筒分层开挖方式的可行性,实现盲区位置30 MPa岩层的高效切削,解决了矩形断面软土与岩层复合地层全断面开挖难题;同时,针对复合地层土舱下部搅拌与出渣难题,采用了复合地层滚筒与螺旋输送机联合出渣技术,并基于计算流体力学(CFD)对滚筒进行排渣特性分析,结果表明当采用双螺旋排渣结构,且螺距在900 mm左右时,排渣效率最高,能够实现复合地层矩形断面土舱高效排渣;最后,通过工业性试验,验证复合地层分层开挖及联合出渣技术的可行性,为复合地层矩形顶管机应用提出了新的解决方案。In this study,the technical schemes of rectangular pipe jacking machine in different composite strata are discussed.Based on the underpass express-line tunnel project at Tiangong Palace in Chongqing,China,the design and application of key systems such as excavation and mucking of rectangular pipe jacking machines in soft soil and rock composite strata are introduced.A layered excavation method for composite strata is proposed for the first time,and a blind area excavation device(rock-breaking roller)is developed.Based on finite element and industrial test analysis,the feasibility of the layered excavation method of composite multicutterhead+roller is verified,realizing the high-efficiency cutting of 30-MPa rock strata in the blind area and successfully implementing rectangular pipe jacking in full-face composite strata of soft soil and rock.Meanwhile,the combined mucking technology of the roller and the screw conveyor is developed for mixing and mucking in the lower part of the excavation chamber in composite formation.The mucking characteristics of the roller are analyzed based on computational fluid dynamics.The results show that the maximum mucking efficiency is achieved when the twin-screw mucking structure is adopted with a distance of~900 mm between the two screws.Finally,the feasibility of layered excavation and combined mucking technology in composite formation is validated through an industrial test,presenting a new solution for the application of rectangular pipe jacking machines in composite formation.
关 键 词:矩形顶管机 复合地层 盲区开挖装置 破岩滚筒 开挖技术 出渣技术
分 类 号:U455[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.28