An Optimization Method for Cable Tension of Cable-stayed Bridges

在线阅读下载全文

作  者:蒲洁 李江 王天琪 雍正阳 巩海周 PU Jie;LI Jiang;WANG Tianqi;YONG Zhengyang;GONG Haizhou(Southwest Company of China Construction Eighth Bureau,Chengdu 610041,China)

机构地区:[1]中建八局西南公司,成都610041

出  处:《交通科技》2023年第5期57-61,共5页Transportation Science & Technology

摘  要:针对斜拉桥建设工期紧、二次调索工作量大、张拉工作耗时较长等问题,提出一种索力张拉优化方法。该方法以主梁上、下缘应力和成桥索力为控制目标,通过对主梁施加临时配重的方式,将二次调索方案转化为一次张拉到位,用以加快施工进度,提高工作效率,实现工程按时通车。以某矮塔斜拉桥为工程背景,通过施工阶段有限元仿真分析,对所提方法的可行性进行验算,结果表明,成桥索力和施工阶段主梁应力均可达到合理要求,验证了所提方法的可行性。In view of the tight construction schedule of cable-stayed bridges,the large workload of secondary cable adjustment and long tensioning work of cable-stayed bridges,etc.,a cable tensioning optimization method is proposed.The method takes the stress at the upper and lower edges of the main girder and the completed bridge cable force as the control target,and transforms the secondary tensioning scheme into a single tensioning in place by applying temporary counterweight to the main girder,so as to speed up the construction progress,improve the working efficiency and realize the opening of the project on time.With a short tower cable-stayed bridge as the engineering background,the feasibility of the proposed method is verified through the finite element simulation analysis in the construction stage,and the results show that the cable force and the stress of the main beam in the construction stage can reach reasonable requirements,which verifies the feasibility of the proposed method.

关 键 词:矮塔斜拉桥 斜拉索 一次张拉到位 临时配重 

分 类 号:U448.27[建筑科学—桥梁与隧道工程] U441[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象