作 者:章飞鸿 ZHANG Feihong(Guizhou Panzhou Water Resources Bureau,Guiyang 553537,China)
出 处:《河南水利与南水北调》2023年第8期124-125,共2页Henan Water Resources & South-to-North Water Diversion
摘 要:为确保水库早日发挥效益,要求水库大坝蓄水试验安全、顺利进行。为此,结合西得泥水库大坝蓄水试验方案设计案例展开分析研究。结果表明,明确水库下闸蓄水试验目的和原则,认识下闸蓄水试验工程概况,重点就水库下闸蓄水前准备工作与水库蓄水要求两方面完成下闸蓄水试验要求,围绕试验步骤和试验应急处理确定水库下闸蓄水试验方案的核心,最后从下闸蓄水试验组织领导小组职责、工作组职责及通信管理等三方面提出水库下闸蓄水试验的组织保障。可为类似水库工程下闸蓄水试验方案提供借鉴参考。In order to ensure the efficiency of the reservoir as soon as possible,it is necessary to carry out the water storage test safely and smoothly.Therefore,the design case of water storage test scheme of Xideni Reservoir Dam is analyzed and studied.The results show that the purpose and principle of reservoir water storage test are clearly defined.The general situation of reservoir water storage test project is understood.The requirements of reservoir water storage test are mainly completed from two aspects of preparation before reservoir water storage and reservoir water storage requirements.The core of the test plan is determined around the test steps and the emergency treatment of the test.Finally,the organization guarantee of reservoir test from three aspects,such as the responsibility of the leading group,the responsibility of the working group and the communication management.It can provide reference for the water storage test scheme of similar reservoir projects.
分 类 号:TV697[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.227