作 者:薛峰 张万里 景帅 任争鸣 XUE Feng;ZHANG Wan-li;JING Shuai;REN Zheng-ming(Huaxin Design Group Co.Ltd.,Wuxi 214072,China)
出 处:《中国给水排水》2023年第20期64-71,共8页China Water & Wastewater
摘 要:太湖流域某城镇污水处理厂设计规模为10×10^(4) m^(3)/d,分为四期建设,主体采用CAST及AAO工艺。提标扩容工程以现状四期工程构筑物提标潜力分析为基础、以混合出水达标排放为目标,从利旧运行状态好的处理设施、优化二期三期生化单元、改造部分闲置构筑物、拆除一期利浦罐腾挪空间、新建深度处理设施、调配衔接各期工程等各维度展开提标扩容设计。预处理采用“粗格栅及提升泵房/细格栅、精细格栅及曝气沉砂池/初沉池”工艺,二级处理工艺采用“改良型Bardenpho生化沉淀池(新一期)、改良AAO及二沉池(二期及四期)、AAO工艺及二沉池(三期)”,深度处理采用“反硝化滤池/高速气浮池/臭氧接触池(新一期及二期)、反硝化滤池/接触消毒池(三期及四期)”工艺,出水混合后部分进入生态缓冲区对尾水进一步处理后再外排进河道。项目完成后规模达12×10^(4 )m^(3)/d,运行状态良好,出水水质达到地表水准Ⅳ类标准。The design scale of a municipal wastewater treatment plant in Taihu Lake basin is 10×10^(4) m^(3)/d.The key processes of the plant are CAST and AAO,and the construction is divided into four phases.The upgrading and expansion project is based on the potential analysis of the current structures belonged to the phaseⅠ-Ⅳprojects and the goal of ensuring the mixed effluent quality meeting the discharge standards.The updrading and expansion design is carried out by considering the aspects such as utilizing well operating treatment facilities,optimizing the biochemical units of phaseⅡand phaseⅢprojects,renovating some idle structures,demolishing the Lipu tanks belonged to phaseⅠproject to release the space,constructing new advanced treatment facilities,coordinating and connecting different phase projects and so on.The pretreatment processes include coarse grid/pumping house/fine grid and finer grid/aerated grit chamber/primary sedimentation tank.The secondary treatment processes consist of modified Bardenpho biochemical sedimentation tank(new phaseⅠproject),modified AAO and secondary sedimentation tank(phaseⅡandⅣprojects),and AAO process and secondary sedimentation tank(phaseⅢproject).The advanced treatment processes are denitrification filter/high speed air floating tank/ozone contact tank(new phaseⅠand phaseⅡprojects),and denitrification filter/contact disinfection tank(phaseⅢandⅣprojects).After mixing,part of the effluent enters the ecological buffer zone for further treatment before being discharged into the river.After the completion of the project,the scale reaches 12×10^(4) m^(3)/d.The wastewater treatment plant operates well and the effluent quality meets the surface water quasi classⅣstandard.
关 键 词:太湖流域 提标扩容 改良型Bardenpho 高速气浮池 生态缓冲区
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.249