地铁轨道工程受限空间物料物流组织模型研究  被引量:1

Study on Material Logistics Organization Model in Confined Space of Subway Track Engineering

在线阅读下载全文

作  者:杨文文 甘二雷 刘治 YANG Wen-wen;GAN Er-lei;LIU Zhi(CCCC-SHEC Railway Construction Co.,Ltd.,Xi'an 710199,China)

机构地区:[1]中交二公局铁路建设有限公司,西安710199

出  处:《价值工程》2023年第32期141-143,共3页Value Engineering

摘  要:基于地铁轨道施工物料运输方法,通过分析受限空间特点、物料时空占用特点和物流组织难点,构建物料运输时长数学模型,提出物流组织优化方法。采用遗传算法求解对比优化前后运输时长,结果表明,优化后的物流组织模式可以减少运输时间19%。Based on the material transportation method of subway track construction,by analyzing the characteristics of confined space,the characteristics of material time-space occupation and the difficulties of logistics organization,the mathematical model of material transportation time is constructed,and the optimization method of logistics organization is proposed.The genetic algorithm was used to compare the transportation time before and after optimization.The results showed that the optimized logistics organization model could reduce the transportation time by 19%.

关 键 词:地铁轨道 受限空间 物料运输时长 计算模型 

分 类 号:F252[经济管理—国民经济]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象