贺西矿软岩巷道底鼓机理及控制技术研究  

Research on the Mechanism and Control Technology of Floor Heave in Soft Rock Roadway of Hexi Mine

在线阅读下载全文

作  者:曹三平 Cao Sanping(Emergency Management Bureau of Lvliang City,Lvliang Shanxi 033000,China)

机构地区:[1]吕梁市应急管理局,山西吕梁033000

出  处:《山西冶金》2023年第10期223-224,227,共3页Shanxi Metallurgy

摘  要:为了解决巷道底板底鼓量大的问题,以贺西矿3316工作面为工程背景,对巷道底板控制技术进行研究,首先通过数值模拟对爆破卸压及切槽卸压效果进行分析,选定爆破卸压方案,后根据现场支护经验选定在巷道600~650 m位置采用底板注浆+锚网索联合支护方案,在巷道650~700 m位置采用底板爆破卸压方案。通过工业化试验对两种方案下巷道底鼓情况进行监测,经过监测发现两种方案均能满足巷道底板控制要求。In order to solve the problem of large floor heave in the roadway floor,the control technology of the roadway floor was studied using the 3316 working face of Hexi Mine as the engineering background.Firstly,the blasting pressure relief and groove cutting pressure relief effects were analyzed through numerical simulation,and the blasting pressure relief plan was selected.Then,based on on-site support experience,a combined support plan of floor grouting and anchor mesh cable was selected at the position of 600~650 meters in the roadway.A floor blasting pressure relief plan is adopted at the position of 650~700 meters in the tunnel.Through industrial experiments,the situation of roadway floor heave was monitored under both schemes,and it was found that both schemes could meet the requirements for roadway floor control.

关 键 词:数值模拟 工业化试验 爆破卸压 注浆支护 

分 类 号:TD353[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象