沿海淤泥及花岗岩地质桩基施工技术研究  被引量:2

CONSTRUCTION TECHNOLOGY OF MARINE SILT AND GRANITE GEOLOGICAL PILE FOUNDATION

在线阅读下载全文

作  者:邓军 Deng Jun

机构地区:[1]中国建筑第二工程局有限公司华南分公司,广东深圳518045

出  处:《建筑技术开发》2023年第12期166-168,共3页Building Technology Development

摘  要:因邻海及人工活动影响,场地内地质条件复杂,钻孔灌注桩施工存在众多施工技术难点,主要表现为地下旧基础等障碍物不明、淤泥质场地不利于大型机械操作、砂层稳定性差易塌孔、地下大小孤石众多、花岗岩入岩难度大等。施工前期通过对施工技术难点逐一提出针对性技术应对措施,确保了在沿海复杂地质条件下桩基施工质量。Due to the influence of the sea and artificial activities,the geological conditions in the site are complex,there are many technical difficulties in the construction of bored pile,which are mainly reflected in the unknown obstacles such as underground old foundation,the silt site is not conducive to large-scale mechanical operation,the sand stability is poor and easy to collapse the hole,the large size of underground isolated stones,granite into the rock difficulty.In the early stage of construction,specific technical countermeasures are put forward to the technical difficulties one by one to ensure the construction quality of pile foundation under the complex geological conditions in the coastal area.

关 键 词:淤泥场地 旋挖入岩 钻孔灌注桩 终孔确认 桩基检测 

分 类 号:U445.551[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象