阳江抽水蓄能电站2号支洞封堵施工技术的研究与实施  被引量:1

Study and Implementation of Sealing Construction Technology for#2 Adit of Yangjiang Pumped Storage Power Station

在线阅读下载全文

作  者:李霞[1] LI Xia(Sinohydro Bureau No.7 Co.,Ltd.,Chengdu Sichuan 610213)

机构地区:[1]中国水利水电第七工程局有限公司,四川成都610213

出  处:《四川水力发电》2023年第6期72-75,共4页Sichuan Hydropower

摘  要:鉴于抽水蓄能电站水头高、灌浆压力大,因而对支洞堵头封堵的整体性、实体及灌浆施工质量要求非常高。阐述了阳江抽水蓄能电站如何通过采用“高流态混凝土+串筒联合”的施工技术措施,解决了封堵混凝土骨料分离、混凝土流动性差及进入钢管底部浇筑不密实等问题;通过智能控制通水冷却速度、温度及在线监测混凝土温度,减少了混凝土裂缝的产生;针对薄弱部位进行补强灌浆,提高了质量保证率。一系列合理、系统性措施的实施,确保了堵头的封堵质量,为水道充水奠定了坚实的基础。The pumped storage power station has high water head and high grouting pressure,therefore,there are high requirements on the integrity,physicality and grouting construction quality of plug sealing.This article explains how the Yangjiang Pumped Storage Power Station solves the problems of sealing concrete aggregate separation,poor concrete fluidity and uncompact pouring at the bottom of the steel pipe by using high-flow concrete+cascade;through intelligent control of the cooling rate and temperature and online monitoring of the concrete temperature,the occurrence of concrete cracks are reduced;reinforcement grouting is carried out for weak parts to improve its quality guarantee rate.The implementation of a series of systematic measures ensures the sealing quality and lays a solid foundation for water filling in the waterway.

关 键 词:阳江抽水蓄能电站 支洞 封堵 施工技术 

分 类 号:TV7[水利工程—水利水电工程] TV52TV554

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象