新建某中型水库工程施工导流方案研究  被引量:1

Research on Construction Diversion Scheme for a New Medium sized Reservoir Project

在线阅读下载全文

作  者:罗明华 LUO Minghua(Power China Gansu Energy Investment Co.,LTD.,Lanzhou 730000,China)

机构地区:[1]中国电建甘肃能源投资有限公司,甘肃兰州730000

出  处:《云南水力发电》2023年第12期344-348,共5页Yunnan Water Power

摘  要:某工程根据具体施工条件,经研究采用分期导流,一期围右岸,二期围左岸的导流设计方案,既能满足工程施工现场导截流和安全度汛的需求,又可以使水库大坝连续快速施工,为安全、可靠、节能、经济且高效的施工奠定基础,使得工程后续阶段的工作顺利开展。Based on specific construction conditions,the project adopts a phased diversion design scheme,with the first phase enclosing the right bank and the second phase enclosing the left bank.It can not only meet the needs of river diversion and safe flood control at the construction site,but also enable the continuous and rapid construction of the reservoir dam,laying the foundation for safe,reliable,energy-saving,economical and efficient construction,and ensuring the smooth progress of the subsequent stages of the project.

关 键 词:中型水库 工程地质 导流方式比选 导流建筑物设计 导流施工 

分 类 号:TV551.1[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象