南方某大型高炉开炉操作实践  

Practice of Opening a Large Blast Furnace in the South

在线阅读下载全文

作  者:贺军位 He Junwei(Guangxi Shenglong Metallurgical Co.,Ltd.,Fangchenggang Guangxi 538000,China)

机构地区:[1]广西盛隆冶金有限公司,广西防城港538000

出  处:《山西冶金》2024年第2期141-144,共4页Shanxi Metallurgy

摘  要:主要对国内某新建大型高炉开炉工作进行了总结。开炉前,由于制粉系统未竣工,开炉后一直全焦冶炼,影响开炉达产进程。通过科学计算开炉料,并在开炉过程进行精准调剂,用时42 h,高炉各项操作参数逐步稳定,达到了安全开炉的目标。This article mainly summarizes the start-up work of a newly built large blast furnace in China.Before the furnace was opened,due to the incomplete powder making system,full coke smelting continued after the furnace was opened,affecting the process of reaching production.Through scientific calculation of the start-up material and precise adjustment during the start-up process,it took 42 hours to gradually stabilize various operating parameters of the blast furnace,achieving the goal of safe start-up.

关 键 词:高炉 开炉 开炉料 炉前 

分 类 号:TF542[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象