作 者:薛璐[1,2,3,4] 马俊杰 王浩璠[1,3,4] 李琳 马劲风 XUE Lu;MA Junjie;WANG Haofan;LI Lin;MA Jinfeng(Carbon Neutrality College(Yulin),Northwest University,Xian,Shaanxi 710069,China;College of Life Sciences,Yulin University,Yulin,Shaanxi 719000,China;National&Local Joint Engineering Research Center of Carbon Capture and Storage Technology,Xian,Shaanxi 710127,China;Department of Geology,Northwest University,Xian,Shaanxi 710069,China)
机构地区:[1]西北大学碳中和学院(榆林),陕西西安710069 [2]榆林学院生命科学学院,陕西榆林719000 [3]二氧化碳捕集与封存国家与地方工程研究中心,陕西西安710127 [4]西北大学地质学系,陕西西安710069
出 处:《环境监测管理与技术》2024年第2期64-68,共5页The Administration and Technique of Environmental Monitoring
基 金:国家自然科学基金资助项目(42304119);陕西省博士后科研基金资助项目(2023BSHEDZZ238);陕西省自然科学研究计划基金资助项目(22JK0636);陕西省重点产业创新链群基金资助项目(2023-ZDLSF-64);榆林市科协青年人才托举计划基金资助项目(20230514);榆林市“科技新星”人才计划基金资助项目(CXY-2022-137);榆林学院高层次人才科研启动基金资助项目(2023GK13);榆林市科技计划基金资助项目(2023-CXY-156)。
摘 要:以鄂尔多斯盆地乔家洼CCS-EOR项目为例,通过工程活动指标分解及选项设计,形成涵盖油区特征、储盖层特征、工程设计、工程监管4大类20个指标的环境风险可能性判定指标体系,利用问卷调查和专家打分法,界定驱油工程环境风险可能性。结合国内外文献分析,开展项目对空气、土壤和微生物、作物、动物及人群等环境风险受体的影响程度界定,基于界定结果,按照风险评估矩阵,对该工程CO_(2)泄漏环境风险水平的评估结论为低风险,在后期运行过程中应强化风险防范与监测。Taking Qiaojiawa CCS-EOR project in Ordos basin as an example,through the decomposition and option design of engineering activity indicators,an environmental risk possibility judgment index system was formed covering 20 indexes in 4 categories,oil region characteristics,reservoir cover characteristics,engineering design and engineering supervision.The possibility of environmental risk in oil displacement engineering was determined by questionnaires and expert scores.At the same time,combined with domestic and foreign literature,the impact of the project on environmental risk receptors such as air,soil,microorganisms,crops,animals and people were defined.The environmental risk level of CO_(2)leakage of the project was assessed as low risk based on the defined results and the risk assessment matrix.Risk prevention and monitoring should be strengthened in the later operation process.
关 键 词:CO_(2)泄漏 风险评估 环境影响 CCS-EOR项目 鄂尔多斯盆地
分 类 号:X820.4[环境科学与工程—环境工程]