作 者:郭莹清 Guo Yingqing(Yuangong Electric Power Technology Co.,Ltd.,Taiyuan Shanxi 030000,China)
出 处:《山西建筑》2024年第9期102-104,共3页Shanxi Architecture
摘 要:采用博超STD-R 5.0软件,研究了不同敷设方式、不同敷设路径、不同电缆走向对变电站全站电缆敷设的影响。从路径规划、长度分割、电缆走向、电缆编码、型号规格、电缆碰撞等不同角度对变电站内电气一次、电气二次、通信电缆敷设进行了分析论证,进而选择较优敷设方式,并更好地指导现场施工,为施工前期设计阶段提供了理论依据。Adopting Bochao STD-R 5.0 software,studied the impact of different laying methods,different laying paths,different cable routeson the overall cable laying of substations.Analyzed and demonstrated the laying of electrical primary,electrical secondary and communication cables in the substation from different perspectives such as path planning,length segmentation,cable routing,cable coding,model specifications,cable collisions,etc..Then choose the optimal laying method,better guide on-site construction,provided theoretical basis for the preliminary design stage of construction.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.222