东曲煤矿长距离掘进巷道贯通测量技术  被引量:1

Break Through Survey Technology of Long-distance Driving Roadway in Dongqu Coal Mine

在线阅读下载全文

作  者:赵辉 ZHAO Hui(Dongqu Coal Mine,Xishan Coal Electricity Co.,Ltd.,Gujiao 030200,Shanxi,China)

机构地区:[1]西山煤电有限责任公司东曲煤矿,山西古交030200

出  处:《能源与节能》2024年第6期161-163,共3页Energy and Energy Conservation

摘  要:东曲煤矿+860水平西翼轨道巷与羊圈港进风斜井在进行贯通测量时,采用了高质量测量仪器,制定了合理的测量方案,并进行了施工测量,使此次贯通顺利接合。导线连测后,在水平重要方向上的闭合差为±406 mm,在高程上的闭合差为±104 mm,贯通测量精度可满足巷道掘进及安全使用需求。High quality measuring instruments were used,a reasonable survey scheme was made,and construction survey was carried out in break through survey to make a smooth connection between Dongqu Coal Mine+860 horizontal west wing track roadway and Yangjuangang inlet inclined shaft.After the conductor was connected,the closure difference in the horizontal important direction was±406 mm,and the closure difference in the elevation was±104 mm.The through survey accuracy can meet the needs of roadway excavation and safe use.

关 键 词:长距离巷道 贯通测量 测量误差 

分 类 号:TD175.5[矿业工程—矿山地质测量]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象