某二类居住项目提前封闭沉降后浇带分析研究  被引量:3

Analysis and Research on Early Closure of Settlement Post-cast Strip for a Type II Residential Land Project

在线阅读下载全文

作  者:赵灿 张靖一 王媛[2] 李伟强[2] Zhao Can;Zhang Jingyi;Wang Yuan;Li Weiqiang(China Railway Construction Real Estate Group North Co.,Ltd.,Beijing 102442,China;Beijing Institute of Architectural Design,Beijing 100045,China)

机构地区:[1]中铁房地产集团北方有限公司,北京102442 [2]北京市建筑设计研究院有限公司,北京100045

出  处:《岩土工程技术》2024年第4期427-430,共4页Geotechnical Engineering Technique

摘  要:北京市大兴区某二类居住用地项目为多栋高层住宅环绕地下车库建筑,为消除差异沉降不利影响,设置了多条沉降后浇带,后浇带的存在严重制约项目工期。根据场地地质条件、地基基础方案以及上部结构荷载分布情况,采用PLAXIS3D进行沉降分析,并结合实际工程经验论证提前封闭沉降后浇带的可行性,结果表明提前封闭沉降后浇带可行。该项目提前封闭了沉降后浇带,实现了预期目的。A Class II residential land project in Daxing District,Beijing is surrounded by multiple high-rise residential buildings and an underground parking garage.To eliminate the adverse effects of differential settlement,multiple post-cast strips were installed.The existence of post-cast strips seriously restricts the project schedule.Therefore,based on the geological conditions of the site,the foundation scheme,and the distribution of loads on the upper structure,PLAXIS3D was used for settlement analysis,and the early closure of settlement post-cast strips was feasibility according to practical engineering experience.The project implemented an early closure of the post-cast strips,thereby accomplishing the intended objectives.

关 键 词:沉降后浇带 差异沉降 施工过程 数值模拟 封闭时间 

分 类 号:TU470[建筑科学—结构工程]

 