检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:韦学敏 许建武[2] Wei Xuemin;Xu Jianwu(Qinzhou Branch of Guangxi Beibu Gulf Port Administration,Qinzhou Guangxi 535008,China;CCCC-FHDI Engineering Co.,Ltd.,Guangzhou Guangdong 510290,China)
机构地区:[1]广西北部湾港口管理局钦州分局,广西钦州535008 [2]中交第四航务工程勘察设计院有限公司,广东广州510290
出 处:《港口航道与近海工程》2024年第4期93-96,101,共5页Port,Waterway and Offshore Engineering
基 金:国家自然科学基金面上项目:海上丝绸之路港口的港湾共振及其引起的系泊船响应研究(52071060)。
摘 要:钦州港目前已有大型码头主要为重力式结构,依托金鼓江作业区19号泊位工程,探讨本地区首座大型高桩梁板码头实施的关键技术问题与对策,并统计分析其实施功效,为当地的港口发展提供一种新的结构选型,有效丰富了技术储备。本文论证了高桩结构的适应性,突出建设中克服的主要难点,包括采用引孔植桩的新工艺,解决了深水裸岩环境下的临时辅助钢管桩与灌注桩钢护筒的施打难题;首次研究了炸礁与灌注桩浇筑的交叉施工机制,填补了行业实践空白;提出了新结构形式下的相应安全管理要求,补充了当地的安全文化建设。The existing large wharves in Qinzhou port belongs to gravity structure.Based on jetty No.19 in Jingujiang operation area,the key technical issues and countermeasures were discussed,which were related to the execution of the first large piled beam-slab wharf in this region,the statistics of real effects were made and analyzed.Such a new wharf structure served as a technical reference,which was beneficial to the port development.The adaptability of piled structure was analyzed,the main difficulties during construction were highlighted,including the application of a new technology of drilling&piling,which solved the difficulty of driving temporary auxiliary steel tubular pile and steel casing into the rock exposed to air in deep water environment.And the crossing construction mechanism of rock blasting and cast-in-situ pile was studied for the first time,which served as a new engineering case.The safety control requirements corresponding to the new structure were put forward,which supplemented local safety education.
关 键 词:高桩梁板码头 引孔植桩 灌注桩 炸礁 交叉施工 安全管理
分 类 号:U656.113[交通运输工程—港口、海岸及近海工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.147.77.120