作 者:王森荣 WANG Senrong(Sinohydro Bureau 5 Co.,LTD.,Chengdu Sichuan 610066)
机构地区:[1]中国水利水电第五工程有限公司,四川成都610066
出 处:《四川水力发电》2024年第4期1-3,9,共4页Sichuan Hydropower
摘 要:两河口水电站大坝为303 m高的砾石土心墙堆石坝,大坝反滤料Ⅰ和反滤料Ⅱ的设计要求与同类工程相比具有包络线范围较窄、制备难度大的特点。阐述了利用DGP1000B电子皮带秤对多种物料实施精确、快速、连续的掺配集中控制,并结合前期取得的经验教训,在瓦支沟反滤料系统中研究并采用了全湿法、两级反滤料掺配原料的方式,为大坝填筑提供了[JP2]质量稳定、可控的反滤料,在施工现场通过精细化施工,保证了大坝高效、优质填筑,取得了提前387 d大坝填筑到顶的佳绩。The Dam of Lianghekou Hydropower Project is a 303 m-high earth-rock fill dam with gravel-soil core.The design requirements for the dam's filter materials I and II have narrower envelopes and greater difficulty in preparation than similar projects.This paper describes the use of the electronic belt scale of DGP1000B to implement precise,rapid,and continuous centralized mixing control of multiple materials.Combined with the experience and lessons learned in the early stage,the full wet method and two-stage filter material mixing method were studied and adopted in the Wazhigou filter material system,providing stable and controllable filter materials for dam filling.Through refined construction at the site,the efficient and high-quality filling of the dam was ensured,and the dam was filled to the top 387 days ahead of schedule.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.145.125.13