高炉非计划休风转停炉生产实践  

Production Practice of Unplanned Shutdown of Blast Furnace

在线阅读下载全文

作  者:卞卫新 吴诚诚 BIAN Weixin;WU Chengcheng(Shaanxi Steel Group Hanzhong Iron and Steel Co.Ltd.,Mianxian 724200,China)

机构地区:[1]陕钢集团汉中钢铁有限责任公司,陕西勉县724200

出  处:《甘肃冶金》2024年第4期69-71,共3页Gansu Metallurgy

摘  要:汉钢2#高炉原定96 h检修,因市场及环保原因超出计划时间复风而转为降料面停炉。本次操作实现了34 h炉况恢复正常,79 h安全停炉。总结其主要操作经验,制定了科学的复风方案和停炉方案,利用铁口氧枪预埋技术快速加热炉缸,恢复过程快速加风引煤气改善炉缸透气性。通过合理的操作参数控制,快速高效的恢复炉况,同时衔接安全顺利的降料面停炉。The No.2 blast furnace of Hansteel was scheduled to be repaired for 96 h,but due to market and environmental reasons,it was changed to a downfeed level shutdown.In this operation,the furnace condition was restored to normal in 34h and the furnace was safely shut down in 79h.The main operation experience is summarized,and the scientific reheating scheme and shutdown scheme are formulated.The furnace cylinder is quickly heated by the technology of iron nozzle oxygen gun,and the gas is quickly added to improve the gas permeability of the furnace cylinder during the recovery process.Through the control of reasonable operating parameters,the furnace condition can be restored quickly and efficiently,and the furnace can be stopped safely and smoothly at the falling level.

关 键 词:高炉 非计划休风 降料面停炉 氧枪 

分 类 号:TF548[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象