山西中部引黄泵站机组调试研究  

Research on pump station unit commissioning of Yellow River Diversion Project in Central Shanxi

在线阅读下载全文

作  者:刘照凯 黄金铎 LIU Zhao-kai;HUANG Jin-duo(Sinohydro Bureau 14 Co.,Ltd.,Kunming 650041,China)

机构地区:[1]中国水利水电第十四工程局有限公司,云南昆明650041

出  处:《水电站机电技术》2024年第9期9-14,169,共7页Mechanical & Electrical Technique of Hydropower Station

摘  要:山西省中部引黄工程3号~7号泵组为国内水利行业中首次规划立式单吸三级蜗壳式离心泵,目前国内大型泵组调试技术经验遗乏,本文研究大型立式单吸三级泵组调试技术,详细介绍了调试工艺原理、试验前检查、输水系统充排水试验、静态调试、无载调试、带载调试的内容和技术要求,为同类型泵组调试提供借鉴。Pump packages No.3~7 of the Yellow River Diversion Project in Central Shanxi are vertical single-suction three-stage pump volute centrifugal pumps planned for the first time in the domestic water conservancy industry of China.At present,there is a lack of application experience in the commissioning technology of large pump packages in China.This paper studies the commissioning technology of large vertical single-suction three-stage pump packages,and introduces in detail the technical principle of commissioning,pre-test inspection,flushing and drainage test of water conveyance system,and content of and technical requirements for static commissioning,no-load commissioning and on-load commissioning,providing reference for the commissioning of similar pump packages.

关 键 词:单吸三级离心泵 双轴线安装 泵组调试 充排水试验 静态调试 

分 类 号:TV675[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象