巴拉卡德锰矿竖井抛渣治水技术研究  

Research on Technique of Water Control through Shaft Dreg Disposal in Barakad Manganese Mine

在线阅读下载全文

作  者:余升红 王忠康 邓骐宁 邹平 赵恰 肖祖荣 王法刚 戴勇 杨星雨 刘正宇 YU Shenghong;WANG Zhongkang;DENG Qining;ZOU Ping;ZHAO Qia;XIAO Zurong;WANG Fagang;DAI Yong;YANG Xingyu;LIU Zhengyu(Zijin(Changsha)Engineering Technology Co.,Ltd.,Changsha 410000,China)

机构地区:[1]紫金(长沙)工程技术有限公司,长沙410000

出  处:《煤炭技术》2024年第9期209-212,共4页Coal Technology

摘  要:井筒被淹没以后,井筒内水位达到静态平衡,在井口以下280 m处,井筒直接淹井深度高达400 m,先进行抛渣11 m,再追排水到抛渣面,在抛渣面浇筑混凝土止浆垫,进行工作面注浆,涌水量由313~500 m^(3)/h,减少到3 m^(3)/h,实际消耗20~40 mm石子810 m^(3),消耗水泥302 t,注浆治水实际工期95 d。After the wellbore was submerged,the water level within the wellbore reached a static equilibrium.At a depth of 280 m below the wellhead,the wellbore was directly flooded to a depth of up to 400 m.First,11 m of debris were cast,followed by drainage to the debris surface.A concrete grout stop pad was poured on the debris surface,and grouting was performed on the working face.The water inflow volume decreased from 313-500 m^(3)/h,ultimately reducing to 3 m^(3)/h.A total of 810 m^(3) of 20-40 mm stones were consumed,along with 302 t of cement.The actual duration of grouting and water control was 95 days.

关 键 词:工作面注浆 抛渣注浆 井筒 

分 类 号:TD745[矿业工程—矿井通风与安全]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象