检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:柳耀琦 刘四新 崔汝卿 祝曾婷 Liu Yaoqi;Liu Sixin;Cui Ruqing;Zhu Zengting(SINOPEC Shanghai Engineering Co.,Ltd.,Shanghai 200120,China;Danzhou State Reserve Petroleum Base Co.Ltd.,Danzhou,Hainan 571741,China)
机构地区:[1]中石化上海工程有限公司,上海200120 [2]儋州国储石油基地有限责任公司,海南儋州571741
出 处:《化工与医药工程》2024年第5期4-11,共8页Chemical and Pharmaceutical Engineering
摘 要:近年来我国建设的地下水封储油洞库均采用了水平水幕系统,水幕系统对于保证洞库水封性至关重要。水幕系统往往进行了大量的水力学试验,但如何拟定合理的试验方法和试验过程,如何有效利用试验数据并合理评价水封效果,还需结合工程实践进行深入研究。文章以某水封洞库为依托,基于单一水幕孔注水-回落试验,对试验的理论背景、试验过程的合理性及数据分析等进行了研究。首先,分析了单一水幕孔注水试验的试验过程和本质特征;然后,基于非稳定流分析原理推导了注水-回落试验的解析方程,并进一步分析了注水试验的水幕孔水压力、注水量与试验时间、岩体渗透参数的关系;最后,以某水封洞库为例,基于试验数据和理论分析,对注水试验的稳压时间进行了计算和分析,并建议了合理的试验过程和稳压时间控制要求。研究结果可为地下水封洞库水幕系统渗透性试验方法的建立提供理论参考依据。In recent years,the horizontal water curtain system has been widely adopted in the construction of underground water-sealed oil reservoirs in China,and the water curtain system is essential to ensure the water sealing of the oil reservoirs.The water curtain system often carries out a large number of hydraulic tests and accumulates a large amount of data.However,how to reasonably formulate test processes,effectively use test data,and reasonably evaluate the water seal effect,are the key issues that need to be studied further by combining engineering practice.This paper studies the issues of the theoretical background of the test,the rationality of the test process,and the data analysis based on the water injection-drop test of a single water curtain borehole in a water-sealed cavern reservoir.Firstly,the processes and characteristics of the water injection-drop test are analyzed.Then,based on the theoretical principle of the unsteady flow,the analytical equations of the water injection-drop test are deduced and further,the relationships among the water pressure of the water curtain borehole,the water injection volume,the test time,and the permeability of the surrounding rock are analyzed.Finally,via the theoretical analysis of the experimental data,the pressure stabilizing time of the water injection test is calculated and analyzed,and reasonable procedures for the water injection-drop test and requirements for pressure stabilizing time control are suggested.The research results can provide a theoretical reference for the establishment of the permeability test method for the water curtain system in underground water-sealed oil storage caverns.
关 键 词:地下水封洞库 水幕系统 注水-回落试验 非稳定流 稳压时间
分 类 号:TE972.2[石油与天然气工程—石油机械设备]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.138.197.104