作 者:许宇栋 Xu Yudong(Shanxi Coal Import and Export Group Zuoyun East Ancient City Coal Industry Co.,Ltd.,Zuoyun Shanxi 037101,China)
机构地区:[1]山西煤炭进出口集团左云东古城煤业有限公司,山西左云037101
出 处:《山西冶金》2024年第8期107-109,113,共4页Shanxi Metallurgy
摘 要:针对特厚煤层综放工作面巷道超前支护难题,以古城煤业有限公司Z107综放工作面为工程背景,对该工作面超前支护25 m范围内单体支柱工作压力进行计算分析。分析结果表明,在该工况条件下,工作面超前10 m范围内采用“一梁三柱”支护方式;工作面超前后15 m范围内,采用“一梁两柱”的单体支护形式。经验证,该支护方式满足现场安全生产需求。In response to the difficulty of advanced support in the roadway of the fully mechanized top coal caving face in the thick coal seam,taking the Z107 fully mechanized top coal caving face of Gucheng Coal Industry Co.,Ltd.as the engineering background,the working pressure of individual pillars within a 25 meter range of advanced support in this face was calculated and analyzed.Analysis shows that under this working condition,within a range of 10 meters ahead of the working face,one beam and three columns are used,and within a range of 15 meters ahead of the working face,a single support form of one beam and two columns is used to meet the safety production requirements on site.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.7