作 者:陈柏荣 CHEN Bairong(The Guangdong No.3 Water Conservancy and Hydro-electric Engineering Board Co.,Ltd.,Dongguan 523000,China)
机构地区:[1]广东省水利水电第三工程局有限公司,广东东莞523000
出 处:《云南水力发电》2024年第11期102-106,共5页Yunnan Water Power
摘 要:黄石盘水库施工汛期时间长,上游压力大且土石坝溢流风险大,针对施工库区的工程地质条件和水文气象条件。制定出一期围堰采用土石围堰,二期围堰采用纵向混凝土围堰和上下游横向土石围堰的施工导流方案,针对汛期风险进行排查,提出合理的施工度汛安全措施和应急预案。为水库后期施工提供了安全支撑。The construction of Huangshipan Reservoir has a long flood season,high upstream pressure,and a high risk of overflow from the earth rock dam.Based on the engineering geological and hydro meteorological conditions of the construction reservoir area,this article proposes a construction diversion plan for the first phase cofferdam to use earth rock cofferdam,and the second phase cofferdam to use longitudinal concrete cofferdam and upstream and downstream transverse earth rock cofferdam.At the same time,it conducts a risk assessment during the flood season and proposes reasonable construction flood safety measures and emergency plans,providing safety support for the later construction of the reservoir.
分 类 号:TV551[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.49