跨海大桥单柱墩盖梁抱箍法施工技术  

Construction Technology of Single Column Pier Cap Beam Clamping and Hooping Method for Cross Sea Bridge

在线阅读下载全文

作  者:陈伟桢 CHEN Wei-zhen(China Railway Construction Group Southern Engineering Co.Ltd.,Guangzhou 510000,China)

机构地区:[1]中铁建设集团南方工程有限公司,广州510000

出  处:《工程建设与设计》2024年第22期127-129,共3页Construction & Design for Engineering

摘  要:对澳氹第四条跨海大桥单柱墩盖梁抱箍法施工工艺流程及施工方法进行阐述与总结,并针对抱箍托架法面临大悬挑及托架下沉问题,利用CAD画图软件设计优化抱箍托架图,利用Midas Civil建立模型进行受力分析,得出各方面受力均满足要求。This article elaborates and summarizes the construction process and method of the single column pier cap beam and hoop method for the fourth cross sea bridge in Aodang. And for the problem of large overhang and bracket sinking faced by the hoop bracket method, CAD drawing software was used to design and optimize the hoop bracket diagram. A model was established by using Midas Civil for force analysis, and it was found that all aspects of the force met the requirements.

关 键 词:跨海大桥 单柱墩盖梁 抱箍法 施工技术 

分 类 号:U445.46[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象