贺斯格乌拉南露天煤矿原煤破碎站移设方案优化  

Optimization of raw coal crushing station relocation plan in Hesigewula South Open-pit Coal Mine

在线阅读下载全文

作  者:王建光 WANG Jianguang(Inner Mongolia Xilinhe Coal Chemical Co.,Ltd.,Wulagai 027299,China)

机构地区:[1]内蒙古锡林河煤化工有限责任公司,内蒙古乌拉盖027299

出  处:《露天采矿技术》2024年第6期69-73,共5页Opencast Mining Technology

摘  要:为了降低贺斯格乌拉南露天煤矿原煤运输成本,实现降本增效目标;采用移设费用补偿法和单位费用最小法建立了原煤破碎站移设步距优化数学模型,结合贺斯格乌拉南露天矿原煤生产系统布置现状与开采规划情况及生产运营指标,对贺斯格乌拉南露天矿原煤破碎站移设步距与移设位置进行了优化;确定了原煤破碎站移设步距722~795 m,破碎站移设周期为5年;电厂输煤系统一级原煤破碎站布设于采场西侧+872 m水平,一号生产系统原煤破碎站移设至采场东帮+812 m水平。In order to reduce the transportation cost of raw coal and achieve the goal of cost reduction and efficiency improvement,a mathematical model for optimizing the relocation step distance of the raw coal crushing station was established using the relocation cost compensation method and the unit cost minimization method.Combined with the current layout and mining planning of the raw coal production system and production and operation indicators of Hesigewula South Open-pit Mine,the relocation step distance and location of the raw coal crushing station were optimized.The relocation step distance of the raw coal crushing station was determined to be 722-795 m,and the relocation period of the crushing station was 5 years.The first level raw coal crushing station of the power plant coal transportation system is located at+872 m level on the west side of the stope,and the raw coal crushing station of No.1 coal production system is moved to+812 m level on the east side of the stope.

关 键 词:露天煤矿 原煤破碎站 移设步距 移设位置 费用补偿法 成本最小法 

分 类 号:TD824[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象