水电工程缆机固定端主机房全地下布置研究与应用  

Research on layout of underground main machine room for cable crane with fixed end and application in hydropower project

在线阅读下载全文

作  者:杨春旭 YANG Chunxu(Hua'neng Lancang River Hydropower Inc.)

机构地区:[1]华能澜沧江水电股份有限公司黄登·大华桥电厂,云南怒江671406

出  处:《大坝与安全》2024年第5期52-56,共5页Dam & Safety

摘  要:某水电站拦河坝位于峡谷河段,两岸地形陡峻,建设中为了降低工程投资,将缆机机房布置于地下,通过上导向轮将牵引及提升系统由竖井引入地下机房,形成了完整的缆机动力及索道系统。该布置形式不仅解决了高边坡的开挖、支护和安全稳定及环保、水保等诸多问题,还降低了工程量和工程投资。本工程的成功经验可为今后缆机设计与安装提供参考和借鉴。A hydropower dam is located in the canyon reach and the terrain on both sides is steep.To re⁃duce project investment,the main room for cable crane is set underground.By use of upper guide pulley and through the shaft,the hauling system and hoisting system are transported into the underground room to provide power and cableway.This scheme not only can solve technical problems such as excavation and support of high slope,environmental protection and conservation of water and soil,but also can re⁃duce investment and work amount,which is worthy of reference.

关 键 词:地下主机房 竖井 锚洞式 缆索起重机 

分 类 号:TV53[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象